Just would like to find out can you set the earned value calculations to use resource units? ev=units vs time. if yes where do i change this, or can you only base the earned value as ev= cost vs time.
EV Calulations
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
just to finalise do i need to set my activity %complete type to Physical? or can i leave it as duration
Hi Dewald,
You can also do the following to calculate EV at resource level :
Hi Dewald.
What I normally do in situations like these, is to set my resource rates to 1$ and to remove all expenses.
The progress percentages you see then are purely based on units. There is also a earned units column if that helps.
Regards,
Arend Kok.