Search

Primavera Date Range

Forum Topic

Hi,Can anyone tell me if Primavera has a specific cut off date for long range portfolio planning?  I know the system can cope with 10-20 years but am not so sure projecting say 80-100 years plus for full lifecycle portfolio planning.  I ran a few sce...

Mar 25, 2021

Creating Resource Curves for Labour Loading Profiles

Forum Topic

 Hello All,I am trying to understand how the Resource Curves are created when using the 21 points shown in the development window.Enterprise > Resource Curves > Add or Modify.[[wysiwyg_imageupload:7689:]]I have a 3 month duration activity with a budg...

Mar 26, 2021

Creating Resource Curves for Labour Loading Profiles

Forum Topic

 Hello All,I am trying to understand how the Resource Curves are created when using the 21 points shown in the development window.Enterprise > Resource Curves > Add or Modify.[[wysiwyg_imageupload:7689:]]I have a 3 month duration activity with a budg...

Mar 26, 2021

Adding One Time Expense

Forum Topic

How can i add one time expenses for a project in the total cost that will add up in the total cost but should not distribute in any activity?

Apr 13, 2020

Primavera EPPM Test Environment Permissions

Forum Topic

I have Primavera EPPM installed on a test server. I have created an EPS, OBS, and user security privileges on the test server. When my IT department moves me to the ‘live’ (or some call it a production) environment. Can I copy the work I created in t...

Apr 14, 2020

Date Center Programme Sample

Forum Topic

Hi all,I was wondering if any of you work in any Data Center project? I was thinking of getting into data center projects and was wondering if any of you have a programme sample for data center, if so I would really appreciate it, if you could share ...

Apr 15, 2020

Apply Global Change with Job Services

Forum Topic

Hi everybody,I would like to apply a Global Change on my schedule, automatically, on a regular basis.The best solution would be to have something possible with the Job Services, but we know that the option is not possible.Does anyone have an idea to ...

Apr 15, 2020

Problems in importing Excel files

Forum Topic

Hi Everybody ,I exported a resource assignement excel file to change budgeted units and other data, when importing the resource is doubled (as shown in the attched image) , i recalculated the assignement costs , but still i will have to manualy remov...

Apr 15, 2020

Assign labor resources by teams in P6

Forum Topic

Hello everyone, I'm establishing a schedule for a new project, where I need to assign labor resources by teams.To simplify the problem, here is a more basic description:  We're building 10 tanks simultaneouslyEach tank is made of 4 shell ringsWe have...

Apr 15, 2020

Primavera Baseline - Even Without It, Data is There, howcome?

Forum Topic

Hi,I understand purpose of having baseline - it is used for comparing actual data with original data. However, I tried this and found out that Primavera maintains baseline data even if we did not create it.1. I make a plan.2. I enter actual progress....

Apr 16, 2020

Specify the interval to summarize and store resource spreads

Forum Topic

Dear MembersCould you please explain to me how does the "Specify the interval to summarize and store resource spreads" function works?I read about it but nothing happen when i changed options.Please help me with explains and template to understand it...

Apr 17, 2020

P6 ver 17 help please, copying WBS

Forum Topic

Morning all, I have a schedule and I'm creating another but I need to copy a section of WBS across both using the same ID's. I wouldn't think this a problem as they're different project IDs but P6 keeps renumbering them.Any ideas if this can be stopp...

Apr 20, 2020

Looking for reviews on Viziya

Forum Topic

Hi all,Hope everyone is safe and well in the current environment.The mining company that I work for is currently looking at a planning and scheduling solution called Viziya WorkAlign Scheduler and I am hoping that there might be some others out there...

Apr 24, 2020

P6 User Preferences

Forum Topic

Hello,Could someone help me to understand what is the diffrence and when or how to use these two options given in user preferences -calculations resource assignments title ?When adding or removing multiple resource assigments on activities1- Preserve...

Apr 24, 2020