Problems in importing Excel files

Hi Everybody ,

I exported a resource assignement excel file to change budgeted units and other data, when importing the resource is doubled (as shown in the attched image) , i recalculated the assignement costs , but still i will have to manualy remove the doubled resource and this will be a tediuos process as there is a lot of af activities .

Hope to find a fix to this problem.

Regards[[wysiwyg_imageupload::]]

Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to Projects DIRECTORY and make sure that your project is open

then click on teh Resources tab at the bottom then look on the lower left where it says Resource Assignment

UNCHECK Resources can be assigned to the same activity more than once. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts