Hi Everybody ,
I exported a resource assignement excel file to change budgeted units and other data, when importing the resource is doubled (as shown in the attched image) , i recalculated the assignement costs , but still i will have to manualy remove the doubled resource and this will be a tediuos process as there is a lot of af activities .
Hope to find a fix to this problem.
Regards[[wysiwyg_imageupload::]]
of course it worked
Thanks Zoltan , it worked.
Regards
go to Projects DIRECTORY and make sure that your project is open
then click on teh Resources tab at the bottom then look on the lower left where it says Resource Assignment
UNCHECK Resources can be assigned to the same activity more than once.