Hi,
Suppose plan has been created and baselined. Actual data has also been entered.
Now, I realize one particular activity had its start/finish date entered very wrong. Is there a way now to change those planned dates?
thanks
Hi,
Suppose plan has been created and baselined. Actual data has also been entered.
Now, I realize one particular activity had its start/finish date entered very wrong. Is there a way now to change those planned dates?
thanks
Hi.
Make Sure that Planned Dates = Current Dates, Do this in Global Change.
Regards.
Thanks Alexandre !!
Hello,
Go to Project, Assign baseline; remove the baseline from Project Baseline and User Baselines when necessay
Go to Project, Update baseline; select the baseline and click Restore to convert the baseline into a new independant project
Open this project, and edit the activity you are mentionning, then re-schedule the project
Open the "current"project again, P6 will close the "new" project
Go to Project, Update baseline; click Add, select the second option and use the "new" project as the baseline for the "current" project
Take care, Stay home
Alexandre