Changing activity start/finish date and duration after being baselined

Hi,

Suppose plan has been created and baselined. Actual data has also been entered. 



Now, I realize one particular activity had its start/finish date entered very wrong. Is there a way now to change those planned dates?

 

thanks

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi.

Make Sure that Planned Dates = Current Dates, Do this in Global Change.

 

Regards.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello,

Go to Project, Assign baseline; remove the baseline from Project Baseline and User Baselines when necessay

Go to Project, Update baseline; select the baseline and click Restore to convert the baseline into a new independant project

Open this project, and edit the activity you are mentionning, then re-schedule the project

Open the "current"project again, P6 will close the "new" project

Go to Project, Update baseline; click Add, select the second option and use the "new" project as the baseline for the "current" project

Take care, Stay home

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts