Search

Salary

Forum Topic

Guys what is the salary for the planner of 3-yrs experience in UAE

Apr 30, 2012

How we calculate VOWD if we have diffrent milestone weightings?

Forum Topic

Dear All Planners, I am working on p6 and I just need to know How we can calculate the VOWD if we given the milestone weightings will be different from the physical progress weightings?   Thank you for any help...   Thank you,

Apr 30, 2012

How to CONVERT all progress citeria to a common unit?

Forum Topic

Dear All Planners,   I nned your help to let me know how I can CONVERT all progress citeria to a common unit - such as money or manhours? With my great thanks for any comments..   Thank you,   Hanson

Apr 30, 2012

budgted values VS Porject baseline values.

Forum Topic

hi there... after completing my plan and baselined it...i started statusing the schedule against my assigned baseline....during collecting field data i noticed that:  my actual units were always above my baseline unitsmy actual cost were always above...

Apr 30, 2012

Planned&Actual %complete

Forum Topic

Dear All Planners,   I know the Actual % Complete in P6 = Physical % complete... But what I don't know how we can calculculate the Planned % complete for the same schedule? What is the procedure.. Thank you for any help..   Hanson

May 1, 2012

Problems assigning specific calendar to only a few tasks?

Forum Topic

Hello!I am trying to assign a 7 day week calendar to 2 tasks on my project. The remaining 100 or so are the standard 5-day 8 hour calendar. However when I drag the '7 day week, Bank Hols & Xmas' to the tasks and release it all of the other tasks chan...

May 1, 2012

Baseline Labour Units

Forum Topic

Gents I have been using a backup of the project as the baseline but found a problem.  The baseline has changed after 8 months of work being completed and tasks and durations changing. This would be considered a re-baselining of the project.     If I ...

May 1, 2012

Scheduled Cost Value

Forum Topic

Hi everybody, How can I gain scheduled cost value for an activity (for example in a column in activity table view), if I have assigened resource curve to activity   Thanks

May 2, 2012

Link task to other projects

Forum Topic

Dears,How can i link tasks between projects on MS Project 2010 Prefessional. I mean, how can i link on "Project A" that 1.2.1 task of "Project A" should start 5 days after 2.2.3 task of "Project B". or do i wish impossible thing ;)Anyone know about t...

May 2, 2012

Planned Start

Forum Topic

I would like to know how to switch on Planned Start and Planned finish date when baselining the projects.

May 3, 2012

MS Project & Sharepoint

Forum Topic

We have multiple project listings (from Sharepoint), spreadsheets and project plans that we are trying to combine into a master project plan. Realizing that SQL Server and data mapping might be required, does anyone have an idea how we can reduce the...

May 3, 2012

Whats Cost % Complete?

Forum Topic

Dear All Planners,I just need to know what is the equation P6 use to calculate the Cost % Complete? Thank you,

May 3, 2012

Whats Cost % Complete?

Forum Topic

Dear All Planners,I just need to know what is the equation P6 use to calculate the Cost % Complete? Thank you,

May 3, 2012

Constructive [overtime] acceleration - Opinions?

Forum Topic

Hi All A topic im sure has been discussed many times before but as new judgments are provided in court and the industry evoles maybe opinions/outlooks change. In terms of constructive accleration such as performing overtime without an official reques...

May 3, 2012

Use of Steps

Forum Topic

All  I have inherited a project where the tasks are very high level.  I have a number of pipes listed under one task and I know the number of metres or feet to be installed in each.   This is relatable to a budget labour unit so I have: pipe 101 - 10...

May 3, 2012

Relationships and the Critical Path. Confused

Forum Topic

Hello!I am new to planning (6 weeks). It is my first job in the construction industry also.I have been taken on as a planning engineer for a small-medium sized main contractor in the UK. I am the only planner currently and I have taken over from an e...

May 4, 2012