I have inherited a project where the tasks are very high level. I have a number of pipes listed under one task and I know the number of metres or feet to be installed in each. This is relatable to a budget labour unit so I have:
pipe 101 - 100 feet and 400 budget labour units
Pipe 102 - 200 feet and 350 budget labour units
Currently the task would have Budget labour units as 750. We get a report that says that 25 feet of pipe 101 is installed and maybe pipe 102 had 50 feet
Is there a way in the steps to represent this info