I would like to know how to switch on Planned Start and Planned finish date when baselining the projects.
Planned Start
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Hemant
Welcome to Planning Planet
If you want to see the baseline bars in seperate rows with start and end dates then there is a switch in > Format > Barchart > Baselines > Show Baselines on their Own Lines.
If you just want a different set of date columns then go to Table Definition and add two more columns for Start and Finish and in the Data Drop Down select the Baseline that you want.
You can also set a column to show the diference in days.
Hope that helps
Best regards
Mike Testro
What I meant was how to switch on the date columns with the "planned start" and "planned finish" dates. I have baselined the project already.