Network Diagrams in P6
Forum TopicI am trying to create a network diagram in P6 showing a summary for some of the WBS sections. Does anyone have an idea how I can do that? Thank you, Donna
I am trying to create a network diagram in P6 showing a summary for some of the WBS sections. Does anyone have an idea how I can do that? Thank you, Donna
dear all, from your experience of loading activities in primavera 6 with cost which method is better 1- Expenses 2- resource let us have discussion about this issue if we go with resources we have to create all BOQ items in resource dictionary ...
Morning all, A colleague has been given a programme to use as a template for another project however she needs to remove all the logic and re-input it in the order the new project will be done. I can't seem to see an easy way to remove the logic with...
Here is the error after importing P6 programme: Type: EprmDBSQLExecutionFailure Event Code: PRMDB-0859-5 Description: PRM DBAccess Error: Database Server Error: The statement has been terminated.Cannot insert the value NULL into column 'actv_code_id...
Hi Can anyone help with the user settings? I am using P6 web and update it by using p6 professional, I have saved the 2 baseline, one project baseline and other as baseline1 by using admin type user. Now I have created one user of read only type “p...
How To fix the Numbder of Helper on Man power histogram, Other Man power like Steel fixer, Mason etc we fix based on their productivity on constructionPlease let me know
Dear All,I just want to ask why group totals of Performance % Complete is not showing ?Is there any settings?Thanks!
The contractor has several activities that are tied to its successor with both an fs and ff ties. Activity 1 – 7/08/13 – 7/10/13 Activity 2 - 7/10/13 – 7/12/13. No lags on either relationship. Would this cause the activity to act like it has a fs-1...
Dear Group members,I am writing to ask if you would be prepared to assist me with my research. I am looking for participants to complete the attached questionnaire, who are currently employed within the construction industry and who either: - have an...
There is a Primavera schedule report that shows predecessor and successor relationships, including type of relationship and lag. I would like to have something visual that would complement this. None of the serious schedules I have built or seen are ...
Hi Guys, Khaled from Canada emailed this great 20-page eBook in to us on how to install Primavera P6 On SQL Server 2012 (no registration required) and we had to share it with you all. You can download it here http://ow.ly/jhn8o Happy installing! Emil...
Hi Guys,Hope all is well.I'm new to p6 and have 3000 acitivites with incorect costing applied to activitiesWould anyone be able to assist on helping me do a global change for removing budgeted cost/Actual cost ?ThanksTom Gouldburn
For purpose of the discussion I am to Call FF Activities all duration type activities that have a FF predecessor link. A FF link can create reverse logic computations that are relevant to scheduling strategy. If the FF link is driving the duration of...
Hi, I am using P6 V7 with Oracle Database. I cannot login into primavera.The following error message coming. ORA-12154: TNS:could not resolve the connect identifier specified I lost complete access to the primavera.I do not want to delete the softwar...
Greetings,can someone tell me what is the function of this feature and how it works. I can't seem to get it to work properly.Thank you,Best Regards,Bogdan
Guys,How to change the start day of the week as Saturday, in P6 Calendar.ThanksAthar Hashmi
Dear All,I would like to ask if there stand alone program in a project?If the engineer insist for stand alone program, what is the best way to deal with it?Thanks all
I am having difficulty working with resource dependent activities; specifically, I have a project-specific series of tasks for which I have some reliable production data and I thought it might be helpful to reconsider activity durations in terms of w...
Respected planners I hail allI am currently working on some projects which is non resource loaded and cost loaded. In my monthly reporting I am expected to report S curve of actual progress against planned. Having gone through this forumn I noticed a...
Dear planners,as in the subject, is there a way to export from expenses (no copy & paste, I aldready know this works fine) the whole cost account ID code? Normally the xls export doesn't display the whole code of cost account ID but just the last par...