Bulk Removal of relationships in a programme

Morning all,

A colleague has been given a programme to use as a template for another project however she needs to remove all the logic and re-input it in the order the new project will be done. I can't seem to see an easy way to remove the logic without going through individual activities. Can anyone point me in the right direction?

Thanks in advance,

Thom

K
Kaif Mohsin 👤 Member for 15 years 3 months

Hi Thomas,

Just copy the programme in P6 and while copying 3 different tabs will appear "Copy Project Options" then "Copy WBS Options" and finally "Copy Activity Options". Under the "Copy Activity Options", untick the Relationships Box and you will get desired result.

Best Regards,

Kaif

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts