The contractor has several activities that are tied to its successor with both an fs and ff ties. Activity 1 – 7/08/13 – 7/10/13 Activity 2 - 7/10/13 – 7/12/13. No lags on either relationship. Would this cause the activity to act like it has a fs-1 relationship?
Activity Relationships
Forum Sponsor
Top Posters
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
Hi Richard
What you have is a ladder effect which is common in manufacturing but has no real place in construction.
It should make no difference to the operation of the logic and it could be beneficial when a progress up date goes beyond the SS link.
Best regards
Mike T.