Activity Relationships

R
Richard Day 👤 Member for 17 years 10 months

The contractor has several activities that are tied to its successor with both an fs and ff ties. Activity 1 – 7/08/13 – 7/10/13   Activity 2 - 7/10/13 – 7/12/13. No lags on either relationship. Would this cause the activity to act like it has a fs-1 relationship?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Richard

What you have is a ladder effect which is common in manufacturing but has no real place in construction.

It should make no difference to the operation of the logic and it could be beneficial when a progress up date goes beyond the SS link.

Best regards

Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts