Quick Update - a process that explains how to update Primavera schedules in quick time

Full Article / Information

"Quick Update" is a process that explains how to update Primavera schedules in quick time.

This presentation will illustrate how to update a schedule in 8 short stages.

  1. Create a Baseline
  2. Switch ON auto schedule
  3. Ensure that Baseline Bar is switched ON
  4. Apply Actuals
  5. Move Data Date Forward
  6. Review IN PROGRESS activities - Update Remaining Duration/Finish Dates
  7.  Review progress of activities on Data Date - Update Start Dates
  8. Switch OFF auto schedule

Author:- David R.V.Forrest

Manoj Wadekar resume

02-09-2014

Dear Sir / Madam

I learned from one of mi colleagues, that one of the oil & gas companies is currently looking for a senior position for “Project Control & Planning Engineer” at their Operations & planning department

Please accept this as my formal application letter.

I believe that my qualification and total twenty two years of multi level experience will be beneficial for your organization as

From last seven years I am working with south PDO as Planning Engineer, and successfully handled the planning activities related to Maintenance, Construction & shutdown for

Michael J. Hondel, P.E., LEED-AP BD+C

Reference Type
Direct Supervisor

Debra works on several projects simultaneously and consistently exceeds expectations.  She instructs training courses within our company on Scheduling / Controls and is the "goto" person if there are any questions in this area.

Debra works with a veriety of external clients and team members and has never had any issues.  She is given a variety of assignments with little notice and consistently finds a way to exceed expectations in stressful work environments.