Assign other progam as a baseline -Synchro

 Hi there,



 have 2.sp files and both has been  exported form P6. one is baseline(No progress) and other is updated .

how can I assign the baseline over the updated one ?



Thank you

R
Renzo Constenla Bravo 👤 Member for 15 years 3 months

Dear colleague:

 

proceed as MR. PT Thomas described.

Just take care that each activity in one file match with the right activity in the other file, through the Act ID.

This is the only way for P6 to joint the current activity with its baseline.

Regards 