Hi there
This is about baselines.
If I don't assign any baseline and I use the current project as such, I have noticed that for the already finished and already started activities the program keeps the original baseline dates one day assigned to those.
What I am doing is I create a copy of a project, I move de DD in the original project, and finally I assigned that copy created as a baseline in the new DD project. I aim to see the finish dates for the ongoing activities as there were beforer moving the DD.
Any suggestions on what I should do?
Thanks,
Frances.
Brilliant. Thanks Gary!!!
Frances,
Go to Admin > Admin preferences > Earned Value and change "Earned Value Calculation" setting to "Budgeted values with current dates"
For more info on this common issue, see Paul Harris' excellent briefing here:
http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf
Cheers,
G