EXPERTS call. Baselines quibble.

Hi there

This is about baselines.

If I don't assign any baseline and I use the current project as such, I have noticed that for the already finished and already started activities the program keeps the original baseline dates one day assigned to those.

What I am doing is I create a copy of a project, I move de DD in the original project, and finally I assigned that copy created as a baseline in the new DD project. I aim to see the finish dates for the ongoing activities as there were beforer moving the DD.

Any suggestions on what I should do?

Thanks,

Frances.