In P3, user can transfer Activity Codes from other Project in the Activity Code Dialog Box. Can someone tell me how to do the same in P6. I can't find the option to do that. Thanks a lot.
Regards,
Eric Chou
In P3, user can transfer Activity Codes from other Project in the Activity Code Dialog Box. Can someone tell me how to do the same in P6. I can't find the option to do that. Thanks a lot.
Regards,
Eric Chou
i have the same problem have u other suggestions? thes methods dan koesnt works out
thanks
Andrea
I have a friend using 8.2 and using the same tool as I am using in 6.2.
Hi Raymund,
Speaking of SDK, is there any available tool of the same for 6.8.2?
Thanks.
Eric,
Use the Import/Export Tool through SDK.