Transfer Activity Codes from other Project

E
Eric Chou 👤 Member for 21 years 11 months

In P3, user can transfer Activity Codes from other Project in the Activity Code Dialog Box.  Can someone tell me how to do the same in P6.  I can't find the option to do that.  Thanks a lot.

 

Regards,

Eric Chou

R
Raymund de Laza 👤 Member for 16 years 6 months
 
I am not using 8.2 but I knowthat the same tool that works with 6.1 also works with 8.2.
I have a friend using 8.2 and using the same tool as I am using in 6.2.
D
D Artagnan 👤 Member for 17 years 8 months

Hi Raymund, 

Speaking of SDK, is there any available tool of the same for 6.8.2?

 