Dear all,
I am recently studying a schedule of a ongoing subway station project ,when i imported the .xer file into P6, the values of "budgeted labor units" and "budgeted nonlabor units" are not equel to the values of the hardcopy file. they are one-eighth of the actual value.
Can anyone tell me how to chang settings to display the right values of the two columns. I think there must be one setting related to this somewhere. Thanks in advance.
Regards ,
Shiguo
Raymund ,
Thank you very much.
Zhang,
The imported file contains a units in hours... In user preferences change your setting of duration units to hour.