Issue regarding the values of "budgeted labor units" and "budgeted nonlabor units"

Dear all,

I am recently studying a schedule of a ongoing subway station project ,when i imported  the .xer file into P6, the values of "budgeted labor units" and "budgeted nonlabor units" are not equel to the values of the hardcopy file. they are one-eighth of the actual  value.

Can anyone tell me how to chang settings to display the right values of the two columns. I think there must be one setting related to this somewhere. Thanks in advance.

 

Regards ,

Shiguo

R
Raymund de Laza 👤 Member for 16 years 6 months

Zhang,

The imported file contains a units in hours... In user preferences change your setting of duration units to hour.