Dear Friends
how can it be possible to make payment application from p6, i thought of one solution ie
to add progress in activity and add boq amount activity by activity as a resource
is there any other solution to this problem ,
your kind comments will be appreciated
Thanks
Umer Mehmood
Abu Dhabi
Umer,
In a current project, although the contractual provisions require a fully cost loaded P6 programme as the basis of payment application for construction, the official application of payment is still prepared in spreadsheet form, to include General Requirements and provisional sums. From the p6 programme, the agreed percent complete for every pay application period is updated in the %complete field, and the actual costs/earned value cost is the pay entitlement for that particular activity.
However, for materials on site, general requirements, provisional items, dayworks and non-construrction items, these are still prepared in excel. The final payment application submitted to the engineer is in spreadsheet format, but includes the p6 updated programme for backup of the construction payment application.
Best regards,