Dear Experts,
Situation:
i am updating the program in weekly/mothly basis but i am not assigning nor maintaining the baseline for so long..
the question is how can i include/assign or maintain the original baseline to the latest updated program??
please help sirs..
Thanks and Regards,
HBS
Bert,
it was a big mistake not to maintain a baseline since before the 1st update!
you can maintain and assign a baseline at any time; you will baseline the current status of the project, the original project is lost for good, unlesse you have printed or exported it before the 1st update!
Hope it helps,
Alexandre