Baseline to Actual Update

B
Bert Ella 👤 Member for 15 years 3 months

Dear Experts,

 

Situation:

i am updating the program in weekly/mothly basis but i am not assigning nor maintaining the baseline for so long..

the question is how can i include/assign or maintain the original baseline to the latest updated program??

please help sirs..

 

Thanks and Regards,

HBS

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Bert,

it was a big mistake not to maintain a baseline since before the 1st update!

you can maintain and assign a baseline at any time; you will baseline the current status of the project, the original project is lost for good, unlesse you have printed or exported it before the 1st update!

Hope it helps,

Alexandre

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts