Progress Updation

Dear Friends 

Me Completed one Base program.

As it is not a resourse loaded program I updated duration percentage.

Here starts the problem

 

Over all actual percentage it is showing .But Over all planned Percentage it is (Shedule percentage ) showing  0

only.In the attachment I shown two Planned Percentage 

1 Performance percentage 

2.Schedule Percentage 

 

Friends please help to getout from this problem.

Please help me in showing Planned VS Actual Percentage 

Over all and Activity wise....

Regards

Arun.V

w.jpg

A
Arun Vasanth 👤 Member for 16 years 7 months

Thanks Raymund

 

Is there any way with out loading resourse.....

 

 

 

Regards

Arun