Dear Friends
Me Completed one Base program.
As it is not a resourse loaded program I updated duration percentage.
Here starts the problem
Over all actual percentage it is showing .But Over all planned Percentage it is (Shedule percentage ) showing 0
only.In the attachment I shown two Planned Percentage
1 Performance percentage
2.Schedule Percentage
Friends please help to getout from this problem.
Please help me in showing Planned VS Actual Percentage
Over all and Activity wise....
Regards
Arun.V

Thanks Raymund
Is there any way with out loading resourse.....
Regards
Arun
Arun,
Make your program a resource loaded and you will get what you requires.
Friends Awaiting your Valuble reply....