When yo do Tools->Update Progress in P3, all your highlighted activities get actualized automatically. I did the same in P6, but the activities didn't get actualized automatically. Can anyone tell me if I'm missing any step or if I'm doing something wrong in P6? Thanks.
Update Progres option in P6 vs Update Progress option in P3
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Try the option apply actuals and update progress. You have to have rights to actuals also check your rights also
Raul,
Are you updating? Can you show the screen shot? Let's see what I can help.
Warren
I think I'm having the same problem. I move the data date, run "update progress" and the activies highlighted move out in time to the new DD. It doesn't do this on all projects but just one right now.
ANY advise on what to configure to get this working correctly again will be GREATLY appreciated.