Update Progres option in P6 vs Update Progress option in P3

R
Raul Santos 👤 Member for 16 years 7 months

When yo do Tools->Update Progress in P3, all your highlighted activities get actualized automatically. I did the same in P6, but the activities didn't get actualized automatically. Can anyone tell me if I'm missing any step or if I'm doing something wrong in P6? Thanks.

W
warren sika 👤 Member for 13 years 4 months

Raul,

Are you updating? Can you show the screen shot? Let's see what I can help.

Warren

J
j ks 👤 Member for 13 years 2 months

I think I'm having the same problem.  I move the data date, run "update progress" and the activies highlighted move out in time to the new DD.  It doesn't do this on all projects but just one right now.

 

ANY advise on what to configure to get this working correctly again will be GREATLY appreciated.

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts