Friends
While loading the resourses when I am entering the budgeted units the duration is changing ..
wats the reason???
Please help.
Rgards
Arun.V
Friends
While loading the resourses when I am entering the budgeted units the duration is changing ..
wats the reason???
Please help.
Rgards
Arun.V
Thank you Shahul
Hi Arun Vasanth
It is due to duration type you assigned to each activity try by using option fixed duration and units
Cheers