Is there anybody who faced to this problem?
I want to calculate Actual percent complete in a project that activities progress base on durations.
how can I do? I think I should read the plan percent complete from Duration % but I don't know that which column is shown Actual % ???
schedule% or original of duration% or... ????
How can get progress in this project type?????
Best Regards
Shima
Dear Azade and other guys
yes, I got it. thank you so much.
Shima
shima jan,
moshkelet hasl shod?
Dear shamiz,
after finalizing the schedule, assign dummy resource, then save it as a baseline, then enter schedule % complete, which will give planned %, to get the actual % Complete enter insert the duration % complete column
shima,
You will find all what you require in 'Percent completes" category.For Planned % Complete you will select column of "schedule % Complete and other are present by there name.just Apply them to your activity window.
Regards
Dear Kumar
thank you for your reply, and from which column I should read the Plan(baseline) % and the Actual (current) % after assigning this dummy resource?
regards
Shima
Dear,
If you are using the % complete type as duration type then i think there is a need to assign atleast a dummy resource for getting the actual %.
The only way to get the actual % without the reosuce assignment is through the physical % type.
for knwoing the actual % complete for this type you can refer to Duration % complete.
Cheers