Calculating Actual percent complete in a project with duration type and without resource and Weight Factor

Is there anybody who faced to this problem?

I want to calculate Actual percent complete in a project that activities progress base on durations.

how can I do? I think I should read the plan percent complete from Duration % but I don't know that which column is shown Actual % ???

schedule% or original of duration% or... ????

How can get progress in this project type?????

Best Regards

Shima

M
mukunda y 👤 Member for 17 years 6 months

Dear shamiz, 

after finalizing the schedule, assign dummy resource, then save it as a baseline, then enter schedule % complete, which will give planned %,  to get the actual % Complete enter insert the duration % complete column

A
AB Timo 👤 Member for 14 years 11 months

shima,

You will find all what you require in 'Percent completes" category.For Planned % Complete you will select column of "schedule % Complete and other are present by there name.just Apply them to your activity window.

 

Regards

S
Shima Zabetian 👤 Member for 15 years 2 months

Dear Kumar

thank you for your reply, and from which column I should read the Plan(baseline) % and the Actual (current) % after assigning this dummy resource?

regards

Shima

K
kumar s 👤 Member for 16 years 4 months

Dear,

If you are using the % complete  type as duration type then i think there is a need to assign atleast a dummy resource for getting the actual %.

The only way to get the actual % without the reosuce assignment is through the physical % type.

for knwoing  the actual % complete for this type you can refer to Duration % complete.

 

Cheers

 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts