Dear All
I have a problem with creating interproject relationships using excel
P6 does not allow me to create them.
Does any one has a work around?
Thanks
Luca
Dear All
I have a problem with creating interproject relationships using excel
P6 does not allow me to create them.
Does any one has a work around?
Thanks
Luca
Just a note for whom may be interested
I used a way around, copied all in one schedule, linked using the excel import and then copied back into the original schedules
Cut and Paste works fine!
L