Interproject Relationship Creation Using Excel

L
Luca Basile 👤 Member for 22 years 11 months

Dear All
I have a problem with creating interproject relationships using excel

P6 does not allow me to create them.

Does any one has a work around?

Thanks
Luca

L
Luca Basile 👤 Member for 22 years 11 months

Just a note for whom may be interested

I used a way around, copied all in one schedule, linked using the excel import and then copied back into the original schedules

Cut and Paste works fine!