Issue with Original Duration in P6 when importing MS Project xlm file

Hi All,

I have a schedule prepared in MSP and I import it to P6 as an xml file. Durations of the tasks in the imported file appears in Original Duration

column (as expected). However, when I change the duration of a task in the Original Duration in P6, the bar in the Gannt Chart does not get longer

or shorter. It gets longer or shorter when I change the duration in the Remaining Duration column.

In fact the Original Duration and Remaining Duration update in Ms Project but after saving the MS File Project as XLM to import to Primavera P6 this

no longer works.

Its as if the calculation in P6 is disabled for this imported Project and I do not know where.

Because If i start a new project in P6 all works as usual and Original Duartion and Remaining Duartion up date automatically

Any ideas whats wrong?

thanks Katrin

 

K
Khaja Sharief 👤 Member for 17 years 10 months

Go to project view. Select the calculation tab and tick mark 'Link budget and at completion for not started activites.'

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts