Hi again!
This time I have milestones that are showing under activities that start on the same date as the milestone. How do I get the milestones above these activities???
Thanks,
Grace
Hi again!
This time I have milestones that are showing under activities that start on the same date as the milestone. How do I get the milestones above these activities???
Thanks,
Grace
Thank you!!! That is awesome, it worked great.
Thanks again,
Grace
hi Grace
did you try what Kumar suggest
i think this is the easiest way
Grace..
One way you can do is sort the activities by actiivity type in groups and sort.
Cheers
Hi Grace
In powerproject you just drag and drop milestones to wherever you want them to be.
This seems like another reason not to bother with P6.
Best regards
Mike Testro