Reports P6 / Per Project and resources

Hi Guys , please I am battaling to produce a report that has the following

Project

       Resources  

          By Name                                    Hours - Monthly allocated

                                              Budgeted

                                              Remaining

 

Please assist

 

regards

K
Kannan CP 👤 Member for 17 years 11 months

Hi,

 

Go to Tools- Report Wizard-New Report.

Tick Time distributed data and select resources.

Now you can select what u want to show in the report.

 

Kannan