Hi Guys , please I am battaling to produce a report that has the following
Project
Resources
By Name Hours - Monthly allocated
Budgeted
Remaining
Please assist
regards
Hi Guys , please I am battaling to produce a report that has the following
Project
Resources
By Name Hours - Monthly allocated
Budgeted
Remaining
Please assist
regards
Hi,
Go to Tools- Report Wizard-New Report.
Tick Time distributed data and select resources.
Now you can select what u want to show in the report.
Kannan