Guys,
I want to enter Total Quantity & productivity, & software need to calculate the manpower requirement based on the quantity & productivity, is there any way?
Mukunda
Guys,
I want to enter Total Quantity & productivity, & software need to calculate the manpower requirement based on the quantity & productivity, is there any way?
Mukunda
P6 is such great software,,, why they dont include this simple concept of Qunatity, procutivity, resource concept...it is the basic planning priniciples.... i think it is crazy software
If you use Spider Project this is SOP.
Not all activities are duration type such as the shipping of a product. Most are driven by the crew daily production, for these we use the Productivity type activity for which activity duration is calculated during scheduling depending upon the assignments, their productivity and their calendars among others.