Software to calculate the Manpower requirement

M
mukunda y 👤 Member for 17 years 6 months

 

Guys,

I want to enter Total Quantity & productivity, & software need to calculate the manpower requirement based on the quantity & productivity, is there any way?

 

Mukunda

M
mukunda y 👤 Member for 17 years 6 months

P6 is such great software,,, why they dont include this simple concept of Qunatity, procutivity, resource concept...it is the basic planning priniciples.... i think it is crazy software

 

R
Rafael Davila 👤 Member for 22 years 3 months

If you use Spider Project this is SOP.

Not all activities are duration type such as the shipping of a product. Most are driven by the crew daily production, for these we use the Productivity type activity for which activity duration is calculated during scheduling depending upon the assignments, their productivity and their calendars among others.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts