Dear Experts...
Summary task % Complete =((Sum of Completed duration of the Baseline Activities Duration)/(Sum of Baseline Activities Duration))*100.
I want to Calcualte the Sumaary task % Complete Based on the Baseline Duration, not based on the Actual Remaining duration. I know to do this in Microsoft Project,...How to do it in primavera using Global Change,,,
I hope my querie is clear...
Regards
Mukunda
Dear Richard,,,, \
Thank u for reply,,, in UDF we can enter only the text or number or interger, we cannot enter the formula in UDF, ,,, can enter the formula only in Global Change,,dont know much about Global change,,,, hope u understand my problem,,,,
Regards
Mukunda
Hi Mukunda,
Try using UDF.
Regards,
Richu
Dear Experts...i am astonishing no reply from day,,, is there no way to do these?
I have inserted user_text 1 Column able to write the text in the activities row, not able to write the text, in the WBS row,,,how to do this,,,
Regards
Mukunda