Baseline dates

M
Manoj VS 👤 Member for 16 years 11 months

Hi

In p6 when a baseline is created from a schedule- start, finish date differ from BL start and BL finish for some activities in that schedule. Is there any reason for this. Please advise me.

 

Thanks in advance.

A
A D 👤 Member for 19 years

It might be because there are actual dates in the baseline schedule. Change the earned value setting under Admin Preferences. (Instead of planned dates you can change it to Current dates).

M
Manoj VS 👤 Member for 16 years 11 months

Dear Mukunda,

My problem is in primavera BL start and BL finish shown is different for some activities without updating

M
mukunda y 👤 Member for 17 years 6 months

Manoj..

Basleline is always Baseline, start & finish dates will change after updating the schedule. It is because of actual dates insertion & rescheduling.

 

Regards

Mukunda

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts