In p6 when a baseline is created from a schedule- start, finish date differ from BL start and BL finish for some activities in that schedule. Is there any reason for this. Please advise me.
Thanks in advance.
Hi
In p6 when a baseline is created from a schedule- start, finish date differ from BL start and BL finish for some activities in that schedule. Is there any reason for this. Please advise me.
Thanks in advance.
It might be because there are actual dates in the baseline schedule. Change the earned value setting under Admin Preferences. (Instead of planned dates you can change it to Current dates).
Dear Mukunda,
My problem is in primavera BL start and BL finish shown is different for some activities without updating
Manoj..
Basleline is always Baseline, start & finish dates will change after updating the schedule. It is because of actual dates insertion & rescheduling.
Regards
Mukunda