Ozgur K 👤 Member for 15 years 7 months

Hi,

I couldn't find a solution regarding the below issue.

I want to show the group total of the data which i organized. After click to this option somehow Primavera calculated the OD as 254 days. 

Start Date:1 Oct 10 A

Finish Date: 13 Jun 11

Data Date: 31 Dec 10

OD=254 , RD=165

Calendar 7 Daywork

When i created a new project that contains only 3 activities which has the same situation (dates, calendar, DD date), Primavera calculated the OD as 256.

What is the difference?

Any help will be appreciated.

Özgür