Hi,
I couldn't find a solution regarding the below issue.
I want to show the group total of the data which i organized. After click to this option somehow Primavera calculated the OD as 254 days.
Start Date:1 Oct 10 A
Finish Date: 13 Jun 11
Data Date: 31 Dec 10
OD=254 , RD=165
Calendar 7 Daywork
When i created a new project that contains only 3 activities which has the same situation (dates, calendar, DD date), Primavera calculated the OD as 256.
What is the difference?
Any help will be appreciated.
Özgür
thanks but Global Calendar is same, 7 daywork.
Group totals are calculated using Global Calendars ---Not Project Calendars.