Could anyone help me to format the timescale of a project made in Primavera 6. Instead of January, February, March I would like to show Month 1, Month 2, Month 3, etc....
Thanks in advance for your help.
Regards,
Jinny Johny
Hi All,
Could anyone help me to format the timescale of a project made in Primavera 6. Instead of January, February, March I would like to show Month 1, Month 2, Month 3, etc....
Thanks in advance for your help.
Regards,
Jinny Johny
Thanks Neil
Jinny Johnny,
You need to select 'show ordinal dates' and set to Month.
Rgds
Walshy