Why does P6 does not show BL2 % Complete

Dear All,

I have assigned two programs as primary baseline and secondary baseline. But i am not able to get the column showing % complete for the secondary baseline program i.e. BL2.

How to solve this problem.

 

Pls do reply.

 

regards,

 

Haresh Jayanth

M
michael ramos 👤 Member for 17 years 3 months

you can try a workaround

assign your BL2 as project baseline and copy the schedule % to UDF using global change (after shifting the data date)

then assign BL1 as project baseline and put your BL2 as primary

now you can compare sched % (BL1) and UDF (BL2)