I have assigned two programs as primary baseline and secondary baseline. But i am not able to get the column showing % complete for the secondary baseline program i.e. BL2.
How to solve this problem.
Pls do reply.
regards,
Haresh Jayanth
Dear All,
I have assigned two programs as primary baseline and secondary baseline. But i am not able to get the column showing % complete for the secondary baseline program i.e. BL2.
How to solve this problem.
Pls do reply.
regards,
Haresh Jayanth
you can try a workaround
assign your BL2 as project baseline and copy the schedule % to UDF using global change (after shifting the data date)
then assign BL1 as project baseline and put your BL2 as primary
now you can compare sched % (BL1) and UDF (BL2)