Hello ,
Explication :
Imagine we have a Labour who works 8h/day and an excavation task ,
the original duration of the task is 10 days
so ,this laber will work a total of 80h ,
If i change the original duration to 2 days ,normally this laber have to work 40h/day => 5 labers/ day
But in the table we have always 8h/day (unit/time) =>one laber only
Thank you
Please check your calennder
it set to 8 hr per day or 10 hr per day.
execavation is a construction activity, in general construction activity time is 10 hr per day. (site working time 10 hr per day)
and Engineering main office worked 8 hr per day , 5 or 6 days per week
first you check calender. ( ste hr / day week, Month , & years)
2nd assign a right cal to activity
3rd check admin preference setting.
may it can work for you.
Thank you !
Why I have to choice fixed Unit and not another type (physical,.....)
I mean how we choice the type : fixed unit or fixed duration,....
thanks
Hi Wahid,
In your case, before changing duration to 2 days ,,,set Duration Type: Fixed Units.
Then change duration.
Best Regards
Shareef A Azeez