When I make down the original duration , the ressource allocation became overloaded but the unit/TIME didn't change

Hello ,

Explication :

Imagine we have a Labour who works 8h/day and an excavation task ,

the original duration of the task is 10 days

so ,this laber will work a total of 80h ,

If i change the original duration to 2 days ,normally this laber have to work  40h/day => 5 labers/ day

But in the table we have always 8h/day (unit/time) =>one laber only

Thank you

 

 

S
Shazia khan 👤 Member for 18 years 1 month

Please check your calennder

 

it set to 8 hr per day or 10 hr per day.

 execavation is a construction activity, in general construction activity  time is 10 hr per day. (site working time 10 hr per day)

 

and Engineering main office  worked 8 hr per day , 5 or 6 days per week

 

first you check calender. ( ste hr / day  week, Month , & years)

2nd assign a right cal to activity

3rd check admin preference setting.

may it can work for you.

W
walid Lahiani 👤 Member for 15 years 7 months

Thank you !

 

Why I have to choice fixed Unit and not another type (physical,.....)

I mean how we choice the type : fixed unit or fixed duration,....

thanks

S
Shareef Abdul Azeez 👤 Member for 20 years 8 months

Hi Wahid,

 

In your case, before changing duration to 2 days ,,,set Duration Type: Fixed Units.

Then change duration.

 

Best Regards

Shareef A Azeez

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts