P6 Roll-up (Performance % CompletE)

Hi All,

In p6, is there any way to roll-up % complete as based on Performance? In my schedule program, some activities are costed/resourced, however,  there is a Owner review period withtout respective costing.... Anayway P6 can roll progress based on a group of activities summarized by WBS? S

 

cenario 1, 6 activities with no resources and only half are complete, what is the base approach to get a summary of progress which ties as close as possible to EVM philsophy??

 

Much appreciate your advice...

C
Craig Freake 👤 Member for 20 years 8 months

Nobody can help??? Or is is just not possible in P6 to roll-up to perfomance % complete without adding cost/resource to any activity??? Want to stay away from Duration % complete...... Much appreciate your suggestions..thanks

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts