Hi All,
In p6, is there any way to roll-up % complete as based on Performance? In my schedule program, some activities are costed/resourced, however, there is a Owner review period withtout respective costing.... Anayway P6 can roll progress based on a group of activities summarized by WBS? S
cenario 1, 6 activities with no resources and only half are complete, what is the base approach to get a summary of progress which ties as close as possible to EVM philsophy??
Much appreciate your advice...
Thanks Shareef!!! WIll try it..
Hi Craige
Check out these forum threads. They have the answers you are looking for
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/418053/s…
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/420413/p…
Best regards
Shareef A Azeez
Nobody can help??? Or is is just not possible in P6 to roll-up to perfomance % complete without adding cost/resource to any activity??? Want to stay away from Duration % complete...... Much appreciate your suggestions..thanks