Budget At Completion in Projects View---Varying
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanx Andrew
Its showing the right data now...
:)
Shareef A Azeez
Shareef,
You may need to summarize your project. Some data (possibly all variable data) stored in the projects view is onlyaccurate against the current plan after the project is summarized.
I run a job service at 2am every night that summarizes my projects to ensure I see the latest info.
Andy