Andrew Dick 👤 Member for 19 years 4 months

Shareef,

You may need to summarize your project. Some data (possibly all variable data) stored in the projects view is onlyaccurate against the current plan after the project is summarized.



I run a job service at 2am every night that summarizes my projects to ensure I see the latest info.



Andy